*Installment No.
|
Payment Plan
|
Other Charges
|
|
At Booking
|
1st
|
Appx. 15%
|
--
|
|
On Excavation/ Bhoomi Poojan
|
2nd
|
5%
|
--
|
|
On Start of Raft Foundation
|
3rd
|
5%
|
1/4th of EDC & IDC
|
|
On Start of Ground Floor Slab
|
4th
|
7.5%
|
--
|
|
On Start of First Floor Slab
|
5th
|
5%
|
1/4th of PLC
|
|
On Start of Second Floor Slab
|
6th
|
5%
|
--
|
|
On Start of Third Floor Slab
|
7th
|
5%
|
1/4th of EDC & IDC
|
|
On Start of Fourth Floor Slab
|
8th
|
5%
|
--
|
|
On Start of Fifth Floor Slab
|
9th
|
5%
|
1/4th of PLC
|
|
On Start of Sixth Floor Slab
|
10th
|
5%
|
1/4th of EDC & IDC
|
|
On Start of Seventh Floor Slab
|
11th
|
5%
|
1/4th of PLC
|
|
On Start of Eighth Floor Slab
|
12th
|
5%
|
1/4th of EDC & IDC
|
|
On Start of Ninth Floor Slab
|
13th
|
5%
|
1/4th of PLC
|
|
On Start of Tenth Floor Slab
|
14th
|
5%
|
½ Club Membership
|
|
On Start of Eleventh Floor Slab
|
15th
|
5%
|
½ Club Membership
|
|
On Start of Twelfth Floor Slab
|
16th
|
--
|
Car Parking
|
|
On start of Last Slab
|
17th
|
7.5%
|
--
|
|
Final On Possession
|
18th
|
5%
|
--
|